NO | Customer/Power Plant | Major Scope | Completion |
---|---|---|---|
KOSPO / Busan Power Headquarters | Installation work of generator 3 Belly Bend | 2009.10 | |
KOWEPO / Taean Power Headquarters | Generator 5 SSC & Flux Prob installation work | 2009.03 | |
Doosan Heavy Industries & Construction | Piping IGL Fabrication Ref G installation work | 2011.04 | |
KOWEPO / Pyeongtaek Power Headquarters | Installation work of subsidiary facilities of Unit 1 | 2011.05 | |
GS Power Bucheon Combined Cycle Power Plant | Plan #3 Boiler, Fan, Comp', etc. Planned preventive maintenance work | 2013.10 | |
KOMIPO / Jeju Power Headquarters | Maintenance work such as Hx, Boiler, Fan, Comp' | 2013.12 | |
Incheon Total Energy | ST Generator Collecting Precision Processing Maintenance Work | 2015.10 | |
GS EPS Power Plant | #3 CEP Upper Brg' replacement | 2015.12 | |
EWP / Dangjin Thermal Power Headquarters | Generator 5,6 Fan disassembly and maintenance | 2015.12 | |
EWP / Dangjin Thermal Power Headquarters | Plan 2 preventive maintenance for water intake and circulation facilities | 2016.04 | |
Incheon Total Energy | Boiler plan preventive maintenance work (Boiler, Fan , Comp’, etc) | 2016.05 | |
EWP / Dangjin Thermal Power Headquarters | Comprehensive office building and subsidiary building machinery annual repair work | 2016.06 | |
EWP / Dangjin Thermal Power Headquarters | Assembling work of turbine 9 equipment (Hx, piping, etc) | 2016.06 | |
Korea District Heating Corporation | Yongin branch Machinery Equipment Plan Prevention and Maintenance | 2017.08 | |
EWP / Dangjin Thermal Power Headquarters | Unit 8 Turbine Facility Plan Prevention and Maintenance Work | 2018. 05 | |
EWP / Dangjin Thermal Power Headquarters | Unit 7 water intake and facility plan preventive maintenance work (TWS, etc) | 2018. 07 | |
KOMIPO / Jeju Power Headquarters | Mechanical facility maintenance work | 2018.10 | |
KOWEPO / Seoincheon Power Headquarters | Unit 7 water intake and facility plan preventive maintenance work (Ex Frame & Bearing Cooling Fan, Oil Tank Vaper Fan, etc) | 2018.11 | |
KOEN / Youngheung Power Headquarters | Unit 3 water intake and facility plan preventive maintenance work (travelling Screen, etc) | 2019.04 | |
EWP / Dangjin Thermal Power Headquarters | Unit 8 water intake and facility plan preventive maintenance work (SLP TWS, CWP TWS Head Section, etc) | 2020.04 | |
KOWEPO / Seoincheon Power Headquarters | Unit 6 water intake and facility plan preventive maintenance work (ST Travelling Water Screen & Line, etc) | 2020.05 | |
EWP/Dangjin Power Headquarters | #7 Absorber Tank Overhaul | 2020.11 | |
Komipo/Boryeong Power Headquarters | #1 CWP Overhaul | 2020.12 | |
GS EPS Power Plant | LNG #4 Generator Rotor Railway Construction | 2023.02 | |
EWP/Dangjin Power Headquarters | #10 Turbine Water Intake Facility Overhaul | 2023.05 | |
GS Donghae Power Plant | #1 Boiler, Turbine Class B Inspection | 2023.06 | |
KDHC/Gimhae Power Headquarters | Mechanical Field Overhaul | 2023.07 | |
Pyeongtaek Energy Service | #2 Generator Fixator Change Work | 2023.10 | |
KNP | #11, 12 GT Generator Rotor Structure Installation Work | 2023.12 | |
KNP | Manufacture safety scaffolding and reinforcement for the generator rotor inlet/output structure | 2024.02 | |
GS EPS | LNG unit 2 GT22 generator rotor inlet railway installation and removal | 2024.05 | |
S-Power Co.,LTD | Structure for GT generator withdrawal | 2024.08 |